June 29 , 2010
World’s Largest Steam-Cracking Furnace Modules Arrive at Singapore from Thailand


MES is awarded this olefins furnaces project with Heurtey Petrochem S.A ,(France) in June 2007 as a part of the ExxonMobil’s largest integrated chemical and refining project.
The full- modularization significantly contributed to shortening delivery period, cost reduction and saving space at site.
MES reached this significant milestone with the arrival and installation of seven world-scale furnace modules on April 27, 2010. Engineering work for the furnace modules took 19 months and was carried out in France and Japan.